Continued From Page
1
We measured the length of the wires
from
the switches to the plugs, then compared that
measurement to the new highbars and
determined that we needed to extend the
wiring 13 inches to insure the proper length.
Add an inch just for safe keeping. This aspect
was measured carefully several times.
Then the left switch loom was attacked
first by drawing the back of the plug on the
stainless bench top with a felt pen. We noted
each color coded wire and position before
removing the wires from the plugs. Do it from
the back so you're in the same position when
you reinstall the wires.
Sure, here's another shot of a diagram,
but it's damn critical to insure the wiring is
correct, so pay attention. Note, that we made
indications on the drawing to indicate the top
from the bottom of the plug.
We added sections of 13-inch wire
staggered in the center of the loom so as not
to stack junctions, and so we maintained the
original color coding. Each junction was
carefully striped 1/4-inch, soldered and sealed
with shrink wrap.
One shot we missed depicted the
wires staggered. That's also crucial so you
don't have junctions bunched together.
Note the handy wire connection holding
tool that Frank had made while working alone
in his garage for ten years. Trying to hold the
connection together, while holding the solder
and the gun is nearly impossible.
The Frank Kaisler, patent pending, wire
junction tool. Send $99.99 to P.O. Box 666,
Hollywood, Calif. Send only rolls of
quarters.
He spoke to an engineer at one point who
didn't cotton to twisting wires. He suggested
that the wires be carefully mated straight on
and soldered. The "Puerto Rican shrink wrap"
as Frank refered to my colorful array of shrink
tubing, was cut so that it would seal 3/8s of an
inch on either side of the connection. Most
chunks of 1/8-inch diameter shrink wrap were
a pinch over an inch long.
We also washed each connection with
alcohol to remove the flux, which could harm
the wires or insulation, then with wet and dry
sandpaper, brushed any sharp edges that
might cut through the shrink wrap.
We cleaned the connections using
alcohol with this brush trimmed in half to
make the bristles stronger.
After each wire was carefully soldered and
prepped we covered it with shrink wrap, then
using Frank's handy tool we heated the area
and moved onto the next stage.
Then the looms were carefully covered
with
additional 1/2-inch shrink wrap. Finally the
bars were carefully blown out with the air
compressor and wiped clean before the
looms were fed into the grip ends of the bars
(first we wrapped the pin connections with
painter's masking tape and created a guiding
point).
I used a painters masking tape to wrap
the connections and form a guiding point. I
didn't want to use a tape that would require
awkward or violent stripping to remove it
(which could damage the wiring).
Feeding the wiring into the bars from
the grip end.
Once carefully pulled through the bars and
the switch housings positioned, we began
the process of installing the connector pins.
Gently pulling the wires from the
bottom of the bars.
After making sure the wires are exactly
in the right position we snugged down the torx
screws, but not permanently.
While refering to the diagram on the
bench we carefully replaced the wires in the
bottom of each plug.
Note the wedged caps that force each
wire clip into a locked position.
This depicts the same procedure from
the other side of the bars. What a great shot,
huh?
Only then could we snap the plug back
into place on the bike. Of course the plug
colors matched.
This was a nervous time. We had
extended 8 and 9 wires respectively (on each
side of the bars), carefully worked them
through the bars and guided them out the
bottom. As we replaced the plugs the sweat
beaded on my brow. Had I correctly soldered
each wire? Was each wire replaced in the
plugs properly? Did I call a wire white with
gray stripe, when it was actually white with
blue stripe? It had taken almost four hours to
complete the operation on the left side of the
bars.
We put the levers in place just to check
the position and see if we didn't blow it. It was
cool.
After a needed lunch break we tackled
the right side of the bars with the same
procedure. Now with the wiring installed in the
bars they were returned to the motorcycle. I
swung my leg over the 100th anniversary
Cobra-styled seat and perched my ass down.
Frank turned the ignition switch on, "try it out,"
he said.
Torquing the bars down to 15 foot
pounds. Torque the front Allens down first,
then the rear according to Pablo.
Continued On Page
3